GRAPHIC: Link to International Mold Steel welcome page.
CONTACT US  
800.625.6653  
 
Home | About Us | What's New | Newsroom | Videos | Contact Us
 

HOME --> DIE CAST & FORGING STEELS --> DH21 --> HEAT TREAT

Die Cast & Forging Steels

DH21

DH21

Click here for
additional information
on DH21 Heat Treat
Click here for
printable PDF

Heat Treatment:

Deformation in Heat Treat

DH21 Heat Treat

DH21 Heat Treat – DH21 is a heat treatable air hardening premium hot work die steel with high toughness and heat check resistance and was developed with aluminum diecasting in mind. Its heat treat process is broken down into two segments, hardening & tempering. The hardening segment is best performed in a vacuum furnace with high pressure quench capabilities.

Vacuum Austenitize & Gas Quenching – DH21 should first be preheat at a rate of less than 220° C (400° F) per hour and held at 800° C (1,475° F) to 850° C (1,560° F) until the tools are uniformly heated from surface to core to within 60° C (100° F) and then increased to 1,030° C ±10° C (1,885° F±18° F) to austenitize otherwise known as soaking the tool.

When distortion in heating is concerned for large or complicated geometry parts, a double pre-heating is recommended: The first pre-heat is at 550° C (1,020° F) to 650° C (1,200° F) and the second at 800° C (1,470° F) to 850° C (1,560° F). The temperature should be allowed to equalize from the surface to the center of the part in each step before proceeding up to the austenitizing temperature.

Once the part reaches 1030° C (1,885° F) and is fully equalized in temperature, the holding time is 30 minutes. In cases where it is difficult to measure the temperature of the center of the part, the holding time from when the atmosphere reaches to 1030° C (1,885° F) should be as shown in the Table considering the delay of the rise in the center temperature. As the time required for equalization of the temperature is ruled by furnace size, loading weight, heating method and so on, holding time is allowed to justify by the recommendation in the Table.

After austenitizing, the part will need to be quenched in inert high pressure gas (generally in nitrogen) to rapidly cool with at least 5 times atmosphere pressure (5 bar) or high velocity equivalent, however 10 bar pressure is recommended. The cooling rate at the center of the part should be at least 5° C (9° F) per minute in the temperature range of 500° C (930° F) to 200° C (390° F) to obtaining suitable toughness.

An interrupted quench is preformed by temporarily halting the cooling process between 450° C and 400° C (840° F and 750° F) to allow the temperature throughout the part to equalize within 110° C (200° F) before continuing the rapid quench. This interrupted quench is recommended to reduce the distortion in quenching. The part should be immediately tempered once it has reached 65° C to (150° F) to 45° C (120° F).

Using Thermocouples - It is important that efforts be taken to measure temperatures at the center of the part throughout the heat treat process. Inserting a thermocouple in the center of the part insures that the entire part has reached the desired temperature before proceeding to the step in the heat treat process. The initial design should allow for the insertion of a thermocouple when possible. Water lines often make excellent locations for thermocouples. Be sure to pack thermocouple holes with a refractory fiber material to help prevent false readings. If the geometry of the part does not accommodate such a feature, it is recommended that a dummy part of similar shape and mass with a thermocouple mounted in the center be used as a temperature control.

There are two ways to use this control information. The first way is to run the part side by side with the dummy part using it to measure the temperature at the center of the part throughout the heat treat process. Realizing that this may not be practical when heat treating large parts, the second way is to cycle the dummy part through the heat treating process while documenting the times it takes for the tool to reach the desired temperatures and use that data to run the actual part. Thermocouples are useful in both the hardening and tempering processes.

Other Quenching Methods - As an alternative to vacuum furnace with gas quench, an atmosphere controlled furnace can be used for austenitizing. The holding time is recommended to be a little longer than that of a vacuum furnace. In this case salt bath or oil bath is used as quenching media to obtain quenching rate higher than 3° C per minute in the range of 500° (930° F) to 200° C (390° F).

Generally, the quench rate should be as rapid as possible to obtain optimum balance of strength and toughness. Quenching too fast, however, may cause distortion and cracking. In controlling the cooling rate by vacuum furnace quenching, it must be considered not only gas pressure, but also gas flow, its rate, heat exchanger efficiency, gas running path and so on.

Tempering – DH21 requires at least two tempers. however triple tempering is recommended for large parts. Preferably, tempering is performed in air convection or atmosphere type furnace however can also be vacuum tempered when aided by the use of thermocouples and special care is taken to monitor temperatures.

The first tempering temperature is 550° C (1,022° F) to 650° C (1,200° F). 580° C (1,075° F) to 600° C (1,110° F) is generally applied for die casting molds. Second tempering is carried out at 550° C (1,022° F) to 650° C (1,200° F) depending on the required hardness. If the resulting hardness is higher than specified, hardness, it can be decreased by a third tempering. When the hardness meets the specification by second tempering, the third tempering is done at 30° C (54° F) to 50° C (90° F) lower than that of the second.

Holding time after atmosphere temperature reaches aimed temperature is 60 minute per 25mm (1 inch) in thickness in cross section with a minimum tempering time of 2 hours.

Note: As with any tool steel, actual heat treat results may vary depending on the circumstances of each application. Therefore the information pertaining to this document is given as a starting point and may require modification based on the size of a given load, fixturing, and equipment capabilities therefore some adjustments in the process may need to be developed and fine tuned base on you combination of circumstances to achieve optimum. Empirical data from heat treating other hot work grades of similar size in specific equipment can be helpful in developing optimum heat treat process for DH21.

Annealing and re-hardening – If re-hardening is needed, it is necessary to first re-anneal the part.

Annealing – DH21 can be annealed by uniformly heating the part to between 820° C (1,508° F) and 870° C (1,598° F), and hold for 2 hours followed by a slow cooling at no more than 20° C (36° F) degrees per hour to until the temperature of the part has dropped below 595° C (1,100° F). The part can then be furnace cooled or left in still air to room temperature to complete the annealing process. The part is now ready to be re-hardened.


www.daido.co.jp 

IMPORTANT NOTE Please be advised that Daido Steel shall not be held responsible for damage caused by misunderstanding or improper use of the technical information contained in this brochure. The contents of this brochure may be subject to change without notice. Please inquire of related department for the latest information. No portion of this brochure may be reproduced without express permission of Daido steel.

DH21

Overview

Heat Treatment

Hardness

Mechanical Properties

Resistance

Nitriding

Thermal Conductivity

Testimonials


Click here for a PDF of the DH21 brochure.

 
 
  International Mold Steel, Inc. 
6796 Powerline Drive 
Florence, KY 41042 USA 
Toll Free: 800.625.6653
Tel: 859.342.6000
Fax: 859.342.6006
Sales E-mail: salesdesk@imsteel.com
Literature E-mail: info@imsteel.com
Web: www.imsteel.com

www.imsteel.com